Client: Caddick Construction
Working in accordance with the client’s specification, we were required to apply intumescent paint, to achieve 60 minutes fire protection to the steelwork, of four newly constructed retail units.
A decorative topcoat was applied to manage the aesthetic requirements of the individual retailers; Aldi, M&S, Screwfix and LDF. Multiple Fire stopping methods were utilised, throughout each unit, in order to separate shop floors and back of house.