The expansion: cavity barriers sequenced before the SFS walls
We’re still supporting Tilbury Douglas on the expansion at Waseley Hills, and this time we were engaged on the service penetrations early, before the walls went up.
Reviewing the details, we found that some of the cavity barriers had to be installed before the SFS walls. Left until later, the SFS would have had to come out again to give us access to fit them.
We agreed the sequence with the site team, so the barriers went in at the right point, nothing had to be taken back out, and the programme kept moving.
It’s a small example of what early engagement does: a detail that would have cost time on site was settled by a conversation before it was built.